In the course of the energy turnaround, the expansion, upgrading and increase of the electricity carrying capacity of the transmission grid in the north and east of Germany plays a central role. 50Hertz is currently planning and implementing a number of line projects in Saxony, Saxony-Anhalt and Thuringia. Two of the power grid expansion projects …
Continue reading...380-kV-overhead power line Pulgar-Vieselbach – Power Line Corridor Designation Procedure completed
On 20 December 2019, the official power line corridor designation procedure for the 380-kV-overhead power line Pulgar-Vieselbach was completed as the Federal Grid Agency took its decision regarding the western segment pursuant to §12 of the German Power Grid Expansion Acceleration Act.
Continue reading...